How Cable Tray Size Changes With Cable Spacing

cable tray size

When someone asks us how big a cable tray should be, our first question is always about the cables. Not how many, but which ones. A tray sized from a quantity count has a way of coming back to bite us later, especially on medium-voltage feeders, where the gaps between cables can force a wider tray than anyone expected. 

What We Look at First 

We start with the cable schedule and the manufacturer data sheets. Outside diameter, single-core or multi-core, and weight per foot are the three numbers we want before we draw anything. Weight matters more than people think. A run of big medium-voltage cables is heavy, and the support span the structure allows can rule out a tray system before width even comes up. 

Then there’s electrical feeder routing. How many bends, where the tray enters the equipment, and whether it has to cross a wall all shape the size we end up asking for. 

One thing trips people up: a sizing calculation gives you a minimum. You can’t order a minimum. You order what the manufacturer sells, and sometimes the next size up is wider than the number you worked out. We model the product that was selected, because a width nobody makes is a problem waiting for procurement. 

Fill and Spacing Are Two Different Questions 

We see these mixed up a lot. Fill is how much cable the rules let you put in the tray. Spacing is where each cable sits once it’s in there. A tray can pass on fill and still be too narrow, because the cables have to lay out a certain way across the bottom. A deeper tray doesn’t fix that. Spacing is mostly a width problem. 

Why Spacing Ends Up Touching Ampacity 

Cables carrying current get warm, and a bundle of warm cables has trouble shedding that heat. So the way cables are grouped can feed into the ampacity review. How much depends on the construction, the load, the tray type, and the air temperature around the run. 

Here’s where we draw a line. Spacing can influence the ampacity check, but it doesn’t decide it. That call belongs to the engineer, who also looks at single versus multiconductor cable and which electrical provisions apply. With single-conductor medium-voltage cable, the approved design may require a particular phase arrangement or set gaps. If someone squeezes the cables together to get past a beam, the feeder may no longer match what it was designed for. We’d rather lose a week moving a tray than ask an engineer to approve a layout nobody studied. 

NEC Article 392 covers cable tray systems. Medium-voltage cable can pull in other requirements for ampacity, supports, grounding, and bonding, so we check the edition the project has adopted. We don’t lean on a spacing number we remember from the last job. 

Where Medium-Voltage Trays Cause Trouble

cable tray size

These cables are heavy, so every straight section, fitting, splice, and structural attachment has to carry the load. And bends are where we see problems during clash detection. A tray can run clean down a corridor and then hit a beam right at the turn. Equipment entries do the same thing, especially when several trays come into switchgear or a transformer from the same side. 

Our advice: don’t model a placeholder tray and leave it. The other trades will plan around that width, and when the real tray shows up wider, they’ll all be unhappy with us. 

Getting the Selected Tray Into the BIM Route 

Once the electrical team approves the tray and cable arrangement, electrical BIM services place it in the model at the selected width and depth. Our cable tray modeling includes the bends, supports, and equipment approach as well, since those are the parts that tend to clash. 

A wider tray takes room from somebody. Maybe it’s a duct, a pipe, a beam, or another electrical path. It might need a bigger wall opening or a different hanger setup. That’s what BIM coordination services are for: working it out in the model instead of with a crew standing in the corridor. The model shows the approved plan, but current and spacing rules stay with the electrical designer. 

A Data Center Example 

Picture a medium-voltage route in a data center BIM project, drawn first beside a big supply duct. It fits, because the model still carries a rough early width. Then the electrical review comes back, and the tray that goes with the approved layout is wider. 

Now it reaches into the duct zone. A fitting lands on steel framing. The communications tray next to it has no room left for its supports. That’s the kind of thing we’d rather catch in the model, so we try another elevation and shift part of the route, then update the supports and openings in the same pass.  

Settle the Tray Before You Sign Off the Route 

Our habit is simple. We don’t lock a route until the cable layout and the tray are agreed. On medium-voltage feeders, spacing can make the tray wider and can change what the engineer approves, so a route drawn before that is mostly a guess. Once the tray is settled, BIM tells us quickly whether it fits through the building.

Frequently Asked Questions

  • How do you determine cable tray size?

    We start from the cable schedule: count, diameter, layout, spacing, and weight. Then tray type, supports, route, and any room to add cables later can push the choice up a size.

  • What are standard cable tray sizes?

    Each manufacturer publishes its own widths and depths, so we model the exact product the project picked.

  • How does cable spacing affect ampacity?

    It changes how well cables shed heat. How much depends on the cable, tray, layout, load, and surrounding air, and the engineer makes the final call.

  • What NEC requirements apply to medium-voltage cable tray?

    Article 392 covers cable tray systems. Other NEC sections may apply to the cables, ampacity, grounding, bonding, and installation conditions.

  • How does BIM help coordinate cable tray sizing?

    It shows the approved tray, fittings, supports, openings, and equipment entries next to structure and the other MEP systems before anyone builds anything. 

Does the Selected Tray Fit the Building?

Eracore coordinates cable tray routes using the approved dimensions, supports, bends, openings, and equipment connections.

Table of Contents

Team Eracore

Team Eracore brings field expertise to the forefront of every article. Our content is crafted in close collaboration with BIM leads, project coordinators, and on-site engineers, ensuring everything we publish is grounded in real project experience. Whether it’s coordination insights or modeling strategies, we write to inform, not just impress.

Eracore

Next Steps

You can also schedule a call to discuss your project details