What Is a Motor Control Center and Where Is It Used?

motor control center

A motor control center, usually shortened to MCC, is a single electrical lineup serving a group of motors. Starters, disconnects, overload devices, and circuit protection are housed in separate cabinet sections. Some lineups also contain feeder units or VFDs, depending on the equipment and project design. 

The connected motors may run pumps, fans, conveyors, mixers, or process machinery. Grouping their controls gives electricians and plant staff one place to work. MCC construction varies by project and manufacturer. 

What Sits Inside a Motor Control Center? 

Power enters through a main section and runs along a common bus. Separate units, often called buckets, connect to it and feed their assigned loads. 

A motor unit can include a disconnect, starter, overload protection, and circuit protection. The starter switches the motor. The electrical design sets the protective arrangement. 

Some sections contain variable-frequency drives. A VFD changes motor speed and may be used with pumps, fans, or process equipment. It is not standard in every MCC. 

Other sections may house feeder breakers, meters, or network hardware. The MCC may also exchange operating information with Industrial Control Systems. Controls design and programming are separate parts of the work. 

NFPA 70 covers motors, motor circuits, and controllers. The adopted edition and project documents determine what applies. 

Where Are MCCs Used? 

MCCs are common where many motor loads operate. A manufacturing lineup may serve conveyors, pumps, exhaust fans, packaging machines, and dust collection equipment. Water plants use them for pumps, screens, blowers, and treatment equipment. 

They also appear in process facilities, central plants, mining operations, and large mechanical rooms. Data centers may use them for cooling equipment. Large motors can involve Medium Voltage Systems, which are handled differently from typical low-voltage lineups. 

On Manufacturing Facility Electrical BIM projects, feeders must reach motors across the production floor. The lineup may also connect to Critical Power Distribution where certain loads have a standby or critical source. 

An MCC and a Switchboard Are Not the Same Thing 

Both are electrical lineups, and their contents can overlap. An MCC is arranged around motor control. A switchboard generally distributes power to panels, equipment, and other downstream loads.

Comparison 

MCC 

Switchboard 

Main job 

Controls and protects groups of motors 

Distributes power to downstream circuits and equipment 

Typical loads 

Pumps, fans, conveyors, and process machinery 

Panels, equipment feeders, and mixed electrical loads 

Common equipment 

Starters, overload devices, disconnects, protective devices, and sometimes VFDs 

Breakers, switches, feeder sections, and metering 

Where it is found 

Plants, water facilities, process buildings, and large mechanical systems 

Commercial, institutional, and industrial buildings 

Main BIM concern 

Motor feeders, section order, cable entry, controls, and access 

Incoming and outgoing feeders, cable entry, access, and distribution routes 

The approved shop drawings settle the details. The equipment name alone will not tell the contractor its access, cable-entry, or expansion needs.

The MCC Room Has to Work in Three Dimensions

Wall length is only the first check. Equipment Control Rooms need feeder entry, maintenance access, ventilation, and a replacement route. A lineup can fit on plan and still be difficult to install. 

Bottom-entry conduits must rise under the correct sections. A change in section order can leave stub-ups in the wrong place. Top-entry feeders have to pass tray, steel, pipes, and ducts. 

Cable Tray Modeling shows how feeders approach the room and drop to the lineup. Bends and vertical transitions need space. Electrical Room Layouts must also account for equipment doors, ventilation openings, the room entrance, and planned expansion. 

Electrical BIM Services carry the lineup and feeders. BIM Coordination Services check that work against structure, piping, ductwork, and process services. The electrical designer remains responsible for loads, starter selection, and protection settings. 

A Manufacturing Room Example 

An MCC beside a production line serves pumps, conveyors, exhaust fans, and a dust collector. It fits on the electrical plan. In the combined model, however, a beam crosses the feeder section, a process pipe blocks the conduit drops, and a control panel occupies the expansion space. 

The team checks the latest shop drawings. The control panel moves to another wall, the tray turns before the beam, and the process pipe shifts. Conduit drops can now reach their assigned sections, and the door route remains open. 

The changes go into the model and installation drawings. On BIM for Industrial Facilities, this review matters because process systems, steel, controls, and electrical distribution often share tight rooms. 

The Lineup Is Only Part of the Job 

A motor control center provides a central place for controlling and protecting a group of motors. It is widely used in manufacturing, water treatment, process work, and large mechanical plants. 

For the contractor, the question is whether the lineup, feeders, access, ventilation, replacement route, and expansion space work together. 

Frequently Asked Questions

  • What is a motor control center?

    It is one electrical lineup containing control and protection equipment for several motors.

  • What does an MCC do?

    It sends power to motor circuits through the control and protective equipment specified for each load.

  • Where are motor control centers used?

    Common locations include factories, water plants, process facilities, central plants, and some data centers.

  • What is the difference between an MCC and a switchboard?

    An MCC centers on motor loads. A switchboard handles wider power distribution, though some functions overlap.

  • How does BIM support MCC room coordination?

    BIM shows the lineup, feeder routes, cable entry, access, structure, pipes, and ducts in one coordinated view.

Is the MCC Room Ready for the Actual Lineup?

Eracore coordinates the equipment, feeders, cable entry, service space, and surrounding trades around the approved MCC shop drawings.

Table of Contents

Team Eracore

Team Eracore brings field expertise to the forefront of every article. Our content is crafted in close collaboration with BIM leads, project coordinators, and on-site engineers, ensuring everything we publish is grounded in real project experience. Whether it’s coordination insights or modeling strategies, we write to inform, not just impress.

Eracore

Next Steps

You can also schedule a call to discuss your project details